Building B1 (South half of site)

 

General view of B1 – Column reinforcement in level minus 1.

 

General view of B1 showing minus 1 columns and beams progress.

 

Works within minus 1 level.

 

B1 : Car park lift landing Minus 3

Building B2 (North half of site)

 

General view of B2 from north end.

 

General view of B2 showing columns and beams progress in the Auditorium area

 

Building 2 : Columns and beams at Lower Ground Floor slab in progress.

 

Building B2: general view level minus 3

 

Mockup façade in progress